The Ministry of Ports and Airports announced an additional R$6.7 million for dredging and rock removal at the Port of Cabedelo in Paraíba. Total investment in these works rises to R$71.15 million.

The project includes upgrades to the inner access channel and expansion of the turning basin used for vessel maneuvers. The aim is to improve conditions for accommodating larger vessels.

Under the announced schedule, preliminary and detailed design work is expected to begin in November 2026. Construction is scheduled for March 2027, with estimated completion in July. These dates reflect the published plan and may be revised by the responsible authority.